Supply, Fabrication, Welding, NDT, and Hydrotesting for 2 two lean solvent pumps piping connection
20 inch Natural gas Pipeline for NATGAS
Fabrication, Welding, NDT, Coating, Excavation, Hydrotest, and Drying for 8 KM Natural Gas Pipeline for NATGAS at 6th of October city-EGYPT
Fabrication, Welding, NDT, Painting, and testing for Natural gas Regulators
Fabrication, Welding, NDT, Painting, and testing for Single & Twin stream Natural Gas Regulators.
450 m Jetty Pipeline for LPTT
Engineering, procument, Fabrication, Welding, NDT, Coating, and Hydrostatic testing for underground 450 m 6”& 2″ carbon steel pipeline for Life Petrochem Terminal Tank-LPTT at Suez-EGYPT
10 inch High pressure pipeline Project
Fabrication, Welding, NDT, Coating, and Hydrotesting for 250 m of 10 inch high pressure Natural gas pipeline at EDKU-Egypt
Fabrication, Painting, Installation of 3 Steel Structure Warehouse blue tuna fish Project.
Fabrication, Painting, and Installation of Steel Structure 3 Warehouse for Blue Tuna Fish Project at Marsa Matroh-EGYPT. Total tonnage 200 Ton
Storage Tanks Farm Construction for NHTT
Fabrication, erection, and testing of 10 atmospheric above-ground tanks (9 tanks 13 M Diameter &1 tank 14.5 M diameter ) with height 13 mater with a total weight of 650 Ton for the NHTT Chemical Tank Farm at West PortSaid Port.
API 650 Tanks Farm for NHTT Project-Phase I
Fabrication, Erection, and Hydrotest for 10 Chemical Atmospheric storage tanks according to API 650 (4 tanks 20m diameter, 6 tanks 13.5m diameter) with 13m height. total fabrication weight 1,100 Ton
Jetty Pipelines and Piping system for NHTT Project
Fabrication and erection for aboveground piping 15,000 Dia.Inch C.S (1″:8″ diameter) and 4,000 S.S piping (8″ :1″ diameter) to connect atmospheric tanks with the pump station. Fabrication and erection for 4 jetty CS pipelines and 1 St.St. Jetty pipeline fot connecting…
Modification of the main 20 inch pipeline at October city
Receiving, stringing, welding, NDT, coating, lowering, hydrostatic testing, And Drying for 1 Km pipeline 20” at west sumid- 6th of October city